Planning Conditions on Your Farm: How to Discharge Them
You have permission. Now clear the conditions.
Most planning permissions come with conditions. Some just need following. Others need details approved by the council before work starts, such as materials, landscaping, drainage or a construction plan. Until those are discharged, you cannot lawfully start.
Pre commencement conditions
A condition that says "before development begins" or "prior to commencement" must be discharged first. Starting without approval can leave the whole development unlawful, and can stop the permission being properly implemented before it expires. Read why your footings may not count as a material start.
How the process works
- You apply to the council with the details each condition asks for, and pay the fee.
- The council has 8 weeks to decide, unless you agree longer in writing.
- For many conditions, if the council has not decided after 6 weeks you can serve a deemed discharge notice. If the council still does not decide by the date in the notice, the condition is treated as discharged.
- Deemed discharge does not apply to some conditions, including flood risk, contaminated land and archaeology.
Getting it right first time
Most delays come from details that do not answer the condition fully. Submit everything for all conditions together where you can, and keep the reports specific to your site. Our farm planning consultants in Suffolk and our wider team across the UK discharge conditions on farm permissions.
How Foxes Rural can help
We read each condition, prepare or commission the details needed, submit them and manage the council until every condition is discharged and you can start.